The PMP exam does not ask you to recite formulas. It asks what a number means for the project and what you should do next. So the useful skill is working a calculation quickly and then reading it: a CPI of 0.8 means every dollar spent has earned 80 cents of planned work, and that is the fact the answer options turn on.
This article gives 12 worked problems with every step shown. The definitions are in the earned value management notes and the estimation techniques notes; the full course, built on the July 2026 outline, is on the PMP exam prep page.
Where do calculations appear on the 2026 PMP exam?
The exam has 180 questions in 240 minutes across three domains: People (33%), Process (41%) and Business Environment (26%). The calculation tasks are in Process. The outline's wording is below.
| Process task | Bullet that implies a calculation |
|---|---|
| Task 1, Develop an integrated project management plan | Estimate work effort and resource requirements. |
| Task 6, Plan and manage finance | Quantify risk and contingency financial allocations. Monitor financial variations and work with the governance process. |
| Task 8, Plan and manage schedule | Estimate project tasks (milestones, dependencies, story points). Analyze schedule variation. |
| Task 9, Evaluate project status | Develop project metrics, analysis, and reconciliation. Measure, analyze, and update project metrics. |
PMI's Certification Handbook says calculators are built into the computer-based exam, and you can ask for a handheld one at a test center. No count of calculation questions is published. Expect them to be a small share of the exam, and expect most of them to ask for interpretation, not just arithmetic.
Which formulas should you know?
| Measure | Formula | How to read it |
|---|---|---|
| Planned value (PV) | Budgeted value of the work scheduled to date | Where the plan says you should be |
| Earned value (EV) | Budgeted value of the work actually done (budget x percent complete) | What you have accomplished, in budget terms |
| Actual cost (AC) | What the work done so far actually cost | What you have spent |
| Cost variance (CV) | EV - AC | Negative means over budget |
| Schedule variance (SV) | EV - PV | Negative means behind schedule |
| Cost performance index (CPI) | EV / AC | Below 1.0 means over budget |
| Schedule performance index (SPI) | EV / PV | Below 1.0 means behind schedule |
| Estimate at completion (EAC), typical | BAC / CPI | Current cost performance continues |
| EAC, atypical | AC + (BAC - EV) | Remaining work goes to the original budget |
| EAC, cost and schedule | AC + (BAC - EV) / (CPI x SPI) | Both indexes keep affecting the remaining work |
| Estimate to complete (ETC) | EAC - AC | What the rest of the work will cost |
| Variance at completion (VAC) | BAC - EAC | Negative means a forecast overrun |
| To-complete performance index (TCPI) | (BAC - EV) / (BAC - AC), or (BAC - EV) / (EAC - AC) | The CPI needed on remaining work to hit the target |
| PERT (beta) estimate | (O + 4M + P) / 6 | Weighted toward the most likely value |
| Triangular estimate | (O + M + P) / 3 | Simple average of the three points |
| PERT standard deviation | (P - O) / 6 | Spread of the estimate |
| Total float | LS - ES, or LF - EF | How long an activity can slip without delaying the project |
All worked problems below use these numbers unless the question says otherwise: budget at completion (BAC) $200,000; at the end of month 4, planned value $80,000, earned value $70,000 and actual cost $87,500. Every figure was checked by computing it, and the arithmetic is shown.
Practice problems: earned value
These are original PrepSolution practice questions, not PMI exam items.
Question 1: Variances and indexes
Using the shared figures (BAC $200,000, PV $80,000, EV $70,000, AC $87,500), which statement is correct?
- A. CV is -$10,000 and SPI is 0.80
- B. CV is -$17,500 and CPI is 0.80
- C. SV is -$17,500 and SPI is 0.875
- D. CV is $17,500 and CPI is 1.25
Best answer: B. CV = EV - AC = 70,000 - 87,500 = -17,500. CPI = EV / AC = 70,000 / 87,500 = 0.80. The project is over budget: each dollar spent has earned 80 cents of planned work. For completeness, SV = EV - PV = -10,000 and SPI = 70,000 / 80,000 = 0.875.
- A is weaker. -$10,000 is the schedule variance, not the cost variance, and 0.80 is the CPI, not the SPI.
- C is weaker. It swaps the two variances. SV is -$10,000; -$17,500 is CV.
- D is weaker. It reverses the order of subtraction and division (AC - EV and AC / EV). Both formulas start with EV.
Question 2: Forecasting the total
The sponsor asks what the project will cost if cost performance stays as it has been. What is the estimate at completion?
- A. $217,500
- B. $228,571
- C. $250,000
- D. $273,214
Best answer: C. "Cost performance stays as it has been" means the typical formula: EAC = BAC / CPI = 200,000 / 0.80 = 250,000. The estimate to complete is then EAC - AC = 250,000 - 87,500 = 162,500, and the variance at completion is BAC - EAC = -50,000.
- A is weaker. $217,500 is AC + (BAC - EV), the atypical formula. It assumes the overrun to date will not continue, which is the opposite of the sponsor's assumption.
- B is weaker. $228,571 is BAC divided by the SPI (200,000 / 0.875). The SPI measures schedule, not cost.
- D is weaker. $273,214 uses both indexes, AC + (BAC - EV) / (CPI x SPI). That formula fits when schedule pressure will also affect cost, which the question does not say.
Question 3: A one-time overrun
The overrun so far came from a single equipment purchase that cost more than budgeted. The team expects the remaining work to cost what the plan says. What is the EAC?
- A. $217,500
- B. $250,000
- C. $200,000
- D. $162,500
Best answer: A. When the variance is a one-off, the remaining work is forecast at its budgeted cost: EAC = AC + (BAC - EV) = 87,500 + (200,000 - 70,000) = 87,500 + 130,000 = 217,500.
- B is weaker. $250,000 assumes the 0.80 CPI continues, which the scenario rules out.
- C is weaker. $200,000 is the original budget. It ignores the $17,500 already overspent.
- D is weaker. $162,500 is the estimate to complete under the typical formula, not a total.
Question 4: Cost and schedule together
The team believes the schedule slip will keep pushing up cost on the remaining work. Which EAC fits that assumption, to the nearest dollar?
- A. $250,000
- B. $273,214
- C. $217,500
- D. $285,714
Best answer: B. When both cost and schedule performance affect the remaining work, divide the remaining budget by CPI x SPI: CPI x SPI = 0.80 x 0.875 = 0.70. EAC = AC + (BAC - EV) / 0.70 = 87,500 + 130,000 / 0.70 = 87,500 + 185,714.29 = 273,214.29.
- A is weaker. $250,000 uses CPI only.
- C is weaker. $217,500 assumes no further variance at all.
- D is weaker. $285,714 is BAC / (CPI x SPI), which applies the combined index to work already done as well as the remainder.
Question 5: Can the budget still be met?
The sponsor wants to finish on the original $200,000 budget. What cost performance index must the team achieve on all remaining work?
- A. 0.80
- B. 0.91
- C. 1.00
- D. 1.16
Best answer: D. TCPI = (BAC - EV) / (BAC - AC) = (200,000 - 70,000) / (200,000 - 87,500) = 130,000 / 112,500 = 1.1556, about 1.16. The team has run at 0.80 so far, so hitting 1.16 for the rest of the project would take a large, sustained improvement. That is the conversation to have with the sponsor.
- A is weaker. 0.80 is the CPI achieved so far, not the CPI needed from here.
- B is weaker. 0.91 is the TCPI against a revised EAC of $230,000, which the sponsor has not approved.
- C is weaker. 1.00 would only hold the current variance steady; it would not recover the $17,500 already overspent.
Question 6: A revised target
Governance approves a revised EAC of $230,000. What TCPI does the team now need, to two decimals?
- A. 0.91
- B. 1.16
- C. 0.80
- D. 1.04
Best answer: A. Against a revised target, TCPI = (BAC - EV) / (EAC - AC) = 130,000 / (230,000 - 87,500) = 130,000 / 142,500 = 0.9123, or 0.91. The team can finish on the new target while running slightly over budget on the remaining work.
- B is weaker. 1.16 is the TCPI to the original BAC.
- C is weaker. 0.80 is the CPI to date.
- D is weaker. 1.04 does not come from either TCPI formula with these figures.
Question 7: Earned value for one work package
A $40,000 work package is 60% complete. The team has spent $27,000 on it. What is its cost variance?
- A. -$3,000
- B. $3,000
- C. -$13,000
- D. $16,000
Best answer: A. EV = budget x percent complete = 40,000 x 0.60 = 24,000. CV = EV - AC = 24,000 - 27,000 = -3,000. The work package is $3,000 over budget for the work done.
- B is weaker. The sign is reversed. Spending more than you earned gives a negative CV.
- C is weaker. This subtracts actual cost from the full budget (40,000 - 27,000) and then treats it as a variance, which mixes total budget with work done.
- D is weaker. $16,000 is the budget remaining for the 40% of work not yet done. It is not a variance.
Question 8: Reading the two indexes
A status report shows CPI 1.10 and SPI 0.90. Which is the best reading?
- A. Over budget and ahead of schedule
- B. Under budget and behind schedule
- C. Under budget and ahead of schedule
- D. Over budget and behind schedule
Best answer: B. CPI above 1.0 means each dollar spent is earning more than a dollar of planned work: under budget. SPI below 1.0 means less work is done than planned: behind schedule. For example, EV $99,000, AC $90,000 and PV $110,000 give exactly CPI 1.10 and SPI 0.90. A common cause is work starting late, so less money has been spent.
- A is weaker. It reverses both readings.
- C is weaker. SPI below 1.0 cannot mean ahead of schedule.
- D is weaker. CPI above 1.0 cannot mean over budget.
Practice problems: estimating and schedule
Three-point estimating takes an optimistic (O), a most likely (M) and a pessimistic (P) duration. NASA's Schedule Management Handbook uses the same three points, under the names minimum, most likely and maximum, for schedule risk ranges. The network problem uses this logic: A (3 days) starts the project; B (4 days) and C (7 days) follow A; D (2 days) follows B; E (3 days) follows both C and D.
| Activity | Duration | Predecessor | Early start | Early finish | Late start | Late finish | Total float |
|---|---|---|---|---|---|---|---|
| A | 3 | None | 0 | 3 | 0 | 3 | 0 |
| B | 4 | A | 3 | 7 | 4 | 8 | 1 |
| C | 7 | A | 3 | 10 | 3 | 10 | 0 |
| D | 2 | B | 7 | 9 | 8 | 10 | 1 |
| E | 3 | C, D | 10 | 13 | 10 | 13 | 0 |
Question 9: PERT estimate
A team estimates an activity at 6 days optimistic, 9 days most likely and 18 days pessimistic. What is the PERT (beta) estimate?
- A. 9 days
- B. 10 days
- C. 11 days
- D. 12 days
Best answer: B. PERT = (O + 4M + P) / 6 = (6 + 36 + 18) / 6 = 60 / 6 = 10 days. The standard deviation is (P - O) / 6 = 12 / 6 = 2 days.
- A is weaker. 9 days is the most likely value alone. It ignores the long pessimistic tail.
- C is weaker. 11 days is the triangular average, (6 + 9 + 18) / 3. It is a valid estimate, but not the PERT (beta) one the question asks for.
- D is weaker. 12 days is the midpoint of the optimistic and pessimistic values, which ignores the most likely value.
Question 10: Float on a noncritical activity
In the practice network, how much total float does activity D have?
- A. 0 days
- B. 1 day
- C. 2 days
- D. 3 days
Best answer: B. D has an early start of 7 (after A and B) and a late start of 8 (E must start by day 10, so D must finish by 10 and start by 8). Total float = LS - ES = 8 - 7 = 1 day. It matches the difference between the critical path (13 days) and D's path (12 days).
- A is weaker. Zero float belongs to activities on the critical path, A-C-E. D is on the shorter path.
- C is weaker. 2 days is D's duration, not its float.
- D is weaker. 3 days has no basis in the network.
Question 11: A slip on the shorter path
In the practice network, activity B slips by 2 days. What happens to the project finish?
- A. Nothing, because B is not on the critical path
- B. It moves out by 1 day
- C. It moves out by 2 days
- D. It moves out by 3 days
Best answer: B. B has 1 day of total float. A 2-day slip uses that day and pushes path A-B-D-E to 3 + 6 + 2 + 3 = 14 days, one day longer than the old critical path of 13. The project finishes 1 day later, and A-B-D-E becomes the critical path.
- A is weaker. Being off the critical path protects an activity only up to its float. B has 1 day; the slip is 2.
- C is weaker. The first day of the slip is absorbed by B's float.
- D is weaker. There is no way for a 2-day slip to delay the finish by more than 2 days.
Question 12: Forecasting with velocity
An agile team has 240 story points left in its release backlog and a stable velocity of 30 points per iteration. Assuming the backlog does not change, how many iterations remain?
- A. 6
- B. 7
- C. 8
- D. 10
Best answer: C. Iterations remaining = remaining points / velocity = 240 / 30 = 8. The answer only holds while the backlog and velocity stay stable, so a good answer on the exam also re-forecasts when either changes.
- A is weaker. 6 iterations would need a velocity of 40.
- B is weaker. 7 iterations would complete only 210 points.
- D is weaker. 10 iterations would correspond to a velocity of 24.
How should you study PMP calculations?
- Learn the four base formulas until you can write them without thinking: CV, SV, CPI and SPI. Every other earned value formula is built from EV, PV, AC and BAC.
- Read the EAC question for its assumption before choosing a formula. "Continue as before" means BAC / CPI; "one-time" or "atypical" means AC + (BAC - EV).
- Check the sign and the size of every answer. Below 1.0 and negative are bad news for cost or schedule; above 1.0 and positive are good news.
- Work one network diagram by hand with a forward and backward pass. Once you have done it, float questions take seconds.
- Expect the question after the calculation: what do you do with a CPI of 0.80? On the 2026 exam, the answer usually involves analysing the cause and working with governance, not simply reporting the number.
For how calculations fit into a timed exam, see the PMP time management strategy. For a short, timed check across all domains, the free PMP practice quiz is available.
References
- [1] Project Management Institute (2026). Project Management Professional (PMP) Examination Content Outline, July 2026. PMI. PMI
- [2] Project Management Institute (2026). PMI Certification Handbook. PMI. PMI
- [3] National Aeronautics and Space Administration (2018). NASA Earned Value Management (EVM) Implementation Handbook. NASA Office of the Chief Financial Officer. NASA Office of the Chief Financial Officer
- [4] National Aeronautics and Space Administration (2024). NASA Schedule Management Handbook. NASA Office of the Chief Financial Officer. NASA Office of the Chief Financial Officer
Help us improve this guide
How helpful was this article?
One tap helps us understand what’s useful.
Frequently asked questions
PMI's July 2026 Examination Content Outline does not list formulas, but its Process tasks include monitoring financial variations, analyzing schedule variation and estimating tasks. Those tasks are where earned value, three-point estimating and critical path calculations appear.
Yes. PMI's Certification Handbook says calculators are built into the computer-based exam and that test center candidates may ask for a handheld calculator. Neither the handbook nor the outline mentions a formula sheet, so plan to know the core formulas from memory.
CPI is earned value divided by actual cost and measures cost efficiency. SPI is earned value divided by planned value and measures schedule efficiency. Below 1.0 is unfavourable for both.
Use BAC divided by CPI when current cost performance is expected to continue. Use AC plus (BAC minus EV) when the variance so far is a one-off. Use AC plus (BAC minus EV) divided by (CPI x SPI) when both cost and schedule performance will affect the remaining work.
Add the optimistic estimate, four times the most likely estimate and the pessimistic estimate, then divide by 6. The standard deviation is the pessimistic minus the optimistic estimate, divided by 6.
TCPI is the cost performance index the team must achieve on all remaining work to finish on a target, either the original BAC or an approved EAC. A TCPI well above the current CPI signals that the target is unlikely to be met.
Keep practicing for the PMP.
Review the study tools, access options and price, or start with free practice.
Related Articles
PMP Process Domain: The Largest Domain, Task by Task
Process is 41% of the July 2026 PMP exam. Here are its ten tasks, what each tests, and three worked questions, including an earned value calculation and a contract type choice.
PMP Exam Prep: What the July 2026 Exam Actually Tests and How to Study for It
The PMP exam changed on 9 July 2026 — new domain weights (33/41/26), 240 minutes, case and scenario questions, and a 40/60 predictive-to-adaptive mix. Study for the exam that exists now, not the one your older materials describe.
PMP Agile vs Predictive Questions: How to Tell Which Approach a Question Tests
The PMP exam never labels questions by approach. Learn the signal words, contextual cues, and mental models that separate agile, predictive, and hybrid scenarios so you can select the right answer framework on exam day.