PrepSolution
PMPHigh-YieldProcess 41%
the most math-heavy topic and the easiest points on the exam

Earned Value Management

12

EVM Formulas

Variances, indices, and forecasts

1.0

Target Index

SPI and CPI at 1.0 means on plan

$0

Target Variance

SV and CV at zero means on plan

three curves tell the whole story

The S-Curve

Planned Value sets the runway. Earned Value shows what you really built. Actual Cost shows what it really cost. The gaps are your variances.

todayEVACPVSV −$48kCV −$36kBAC $480k$time →

PV · dashed

what you planned to earn by now

EV · solid

what you actually built, valued in budget $

AC · solid

what you actually spent

how to read this

  • › Three lines. At any point on the timeline, measure the vertical gap between them to see variance.
  • EV below PV (as shown) = you built less than planned. That gap is Schedule Variance (SV).
  • AC above EV (as shown) = you spent more than the value you earned. That gap is Cost Variance (CV).
  • › When a manager asks "how's the project?" this chart answers in 3 seconds — where you planned to be, what you built, what it cost.
  • › EV is always the measuring stick. Everything else compares to it.

The Formula Cheat Sheet

Variances · negative is bad

SV = EV − PV

CV = EV − AC

Indices · below 1.0 is bad

SPI = EV / PV

CPI = EV / AC

Forecasts · three EAC variants

EAC = BAC / CPI · default

EAC = AC + (BAC − EV) · atypical variance

EAC = AC + (BAC − EV) / (CPI × SPI) · cost and schedule

ETC = EAC − AC

VAC = BAC − EAC

TCPI = (BAC − EV) / (BAC − AC)

Worked Example

BAC = $480,000 · PV = $240,000 · EV = $192,000 · AC = $228,000

SV = 192,000 − 240,000 = −$48,000 behind schedule

CV = 192,000 − 228,000 = −$36,000 over budget

SPI = 192,000 / 240,000 = 0.80 · 20% behind

CPI = 192,000 / 228,000 = 0.84 · 84¢ per $1 spent

EAC = 480,000 / 0.84 = $571,429

VAC = 480,000 − 571,429 = −$91,429 projected overrun

Under 1.0 is bad. Over 1.0 is good. Negative variance is bad. Positive variance is good. Memorize this compass before the exam.

Exam Traps

EV is always in the first position

SV = EV − PV, not PV − EV. CV = EV − AC, not AC − EV. SPI = EV/PV. CPI = EV/AC. Memorize it as "EV always on the left or on top." Questions deliberately flip the order to catch you.

SV becomes unreliable at the end of the project

A late project still shows SV = 0 and SPI = 1.0 at completion because all planned value is eventually earned. For late-stage schedule assessment, use schedule-based metrics (earned schedule), not SV/SPI.

Three EAC formulas, three different conditions

BAC/CPI = "current performance continues." AC + (BAC − EV) = "remaining work at original rate." AC + (BAC − EV)/(CPI × SPI) = "both cost and schedule matter." Read the question carefully and match the condition.

TCPI above 1.0 means you have to do better than planned

A TCPI of 1.15 means the team must deliver 15% more efficiently on remaining work than originally estimated. The higher it is, the less realistic. TCPI far above 1.0 is a signal to revise the plan, not push harder.

Above 1.0 is good

CPI and SPI above 1.0 means ahead. Below 1.0 means behind. Positive variance is good, negative is bad.

Do not guess EAC

EAC = BAC/CPI is the default. If the question specifies atypical or one-time variance, use AC + (BAC − EV) instead.

1
PV, EV, AC Are Three Different Dollars

You planned to drive halfway across the country by day 5 and spend $500 (PV). You actually made it only 40% of the way (EV = $400 of planned value earned). But gas was expensive, so you spent $600 (AC). PV, EV, and AC are three different dollar amounts asking three different questions.

2
Variances Tell You the Truth

SV = EV − PV = 400 − 500 = −$100. You are behind schedule by $100 worth of progress. CV = EV − AC = 400 − 600 = −$200. You are over budget by $200. Negative means bad.

3
Indices Normalize the Bad News

SPI = 400/500 = 0.80. You are doing 80% of planned progress. CPI = 400/600 = 0.67. You are getting 67 cents of value for every dollar spent. Below 1.0 means trouble.

4
EAC Predicts the Final Bill

If the same cost problem continues, EAC = BAC/CPI. If total trip budget was $1,000, then $1,000/0.67 ≈ $1,494. You are projected to finish $494 over budget. That is when you call the sponsor.

EV on top, PV and AC on the bottom. Below 1.0 is bad news. BAC/CPI is the default EAC.
reading is not enough, you gotta practice

Ready to test your PMP knowledge?

1,800 practice questions written by certified professionals.

Start Practicing PMP
Reviewed by Chris K., PrepSolution Content Editor, Project Management
Sources verified against PMI 2026 standards
Updated May 2026