Risk questions on the PMP exam rarely ask for a definition. They describe a project, a threat or an opportunity, and a constraint, then ask what the project manager should do or what a number means. You need the vocabulary, but the score comes from choosing well.
This article drills that choice with 12 worked problems. If you are building a full plan, the PMP exam prep course covers every domain with timed mock exams. For the theory behind qualitative and quantitative analysis, use the risk management notes, and for earned value math see the PMP formulas practice set.
Where does risk appear on the July 2026 PMP outline?
PMI's July 2026 Examination Content Outline weights the exam at People 33%, Process 41% and Business Environment 26%. About 40% of items use predictive approaches and the rest are split between agile and hybrid. Risk shows up in three tasks.
| Domain and task | Enablers that involve risk |
|---|---|
| Business Environment, Task 5: Plan and manage risk | Identify risks; analyze risks; monitor and control risks; develop a risk management plan; maintain a risk register; execute a risk management plan; communicate the status of a risk impact on the project |
| Process, Task 6: Plan and manage finance | Quantify risk and contingency financial allocations; manage financial reserves |
| Business Environment, Task 4: Remove impediments and manage issues | Recognize when a risk becomes an issue |
PMI does not publish how many questions come from each task, so treat risk as a theme that can appear in any domain rather than a fixed block of items.
Which terms and formulas do the questions use?
| Term | What it means | Exam signal |
|---|---|---|
| Avoid (threat) | Change the plan so the threat cannot occur or cannot affect the project | Remove the cause, drop the risky option |
| Transfer (threat) | Shift the impact and ownership of the response to a third party | Insurance, warranty, fixed-price subcontract |
| Mitigate (threat) | Lower the probability or impact | Extra testing, prototypes, redundancy |
| Accept (threat or opportunity) | Take no action unless it occurs; active acceptance sets aside a reserve | Low score risks, contingency reserve |
| Escalate (threat or opportunity) | Hand the risk to the level that owns it when it is outside the project's authority | Affects other projects or the organization |
| Exploit / Enhance / Share (opportunity) | Make it certain / raise its probability or impact / partner with a party better placed to capture it | Assign best people, add capacity, joint venture |
| Expected monetary value (EMV) | Probability x impact; threats negative, opportunities positive | Sum across risks to size contingency |
| Contingency reserve | Money for identified risks; part of the cost baseline | Controlled by the project manager under the plan |
| Management reserve | Money for unidentified risks; in the budget, not the baseline | Needs approval through governance |
These are original PrepSolution practice questions, not PMI exam items. Every figure was computed before the answer was written.
Practice questions: calculations
Question 1: Net expected monetary value
A project faces a threat with a 20% probability and a $50,000 impact, and an opportunity with a 30% probability and a $20,000 benefit. What is the combined expected monetary value of the two risks?
- A. -$10,000
- B. +$6,000
- C. -$4,000
- D. -$16,000
Best answer: C. Threat EMV = 0.20 x -$50,000 = -$10,000. Opportunity EMV = 0.30 x $20,000 = +$6,000. Combined EMV = -$10,000 + $6,000 = -$4,000.
- A is weaker. This is the threat alone. The opportunity offsets part of it.
- B is weaker. This is the opportunity alone.
- D is weaker. This subtracts the opportunity instead of adding it. Opportunities carry a positive sign.
Question 2: Sizing a contingency reserve
The risk register lists three threats. The team wants a contingency reserve equal to their combined EMV.
Threat 1: 10% probability, $80,000 impact. Threat 2: 25% probability, $24,000 impact. Threat 3: 50% probability, $6,000 impact. What reserve should they request?
- A. $17,000
- B. $110,000
- C. $5,667
- D. $8,000
Best answer: A. EMV of each threat: 0.10 x 80,000 = 8,000; 0.25 x 24,000 = 6,000; 0.50 x 6,000 = 3,000. Sum = 8,000 + 6,000 + 3,000 = $17,000.
- B is weaker. $110,000 is the sum of the impacts. That reserve assumes every threat happens, which is not what EMV measures.
- C is weaker. $5,667 is the average of the three EMVs. The reserve covers all three, so they are added.
- D is weaker. $8,000 covers only the largest threat.
Question 3: Decision tree
A team must choose between building a component and buying it.
Build: $120,000, with a 40% chance of $30,000 in rework. Buy: $140,000, with a 10% chance of $20,000 in integration fixes. Which option has the lower expected cost?
- A. Buy, because its expected cost is $140,000 against $150,000 to build
- B. Buy, because it has the smaller chance of extra cost
- C. Build, because its base cost is $20,000 lower and the risks cancel out
- D. Build, because its expected cost is $132,000, which is $10,000 less than buying
Best answer: D. Expected cost to build = 120,000 + 0.40 x 30,000 = 132,000. Expected cost to buy = 140,000 + 0.10 x 20,000 = 142,000. Build is lower by $10,000.
- A is weaker. This adds the full $30,000 rework cost to building as if it were certain, and leaves the $2,000 expected integration cost out of buying.
- B is weaker. A lower probability does not settle the choice. The decision tree weighs probability and impact together.
- C is weaker. The conclusion is right but the reasoning is not. The risks do not cancel: they add $12,000 and $2,000.
Question 4: Cost baseline and budget
Work package estimates total $400,000. The team adds a $40,000 contingency reserve for identified risks, and the sponsor holds a $25,000 management reserve. What are the cost baseline and the project budget?
- A. Baseline $400,000; budget $465,000
- B. Baseline $440,000; budget $465,000
- C. Baseline $465,000; budget $465,000
- D. Baseline $425,000; budget $465,000
Best answer: B. The cost baseline includes contingency reserve: 400,000 + 40,000 = 440,000. The budget adds management reserve on top: 440,000 + 25,000 = 465,000.
- A is weaker. This leaves contingency reserve out of the baseline. Contingency for known risks belongs inside it.
- C is weaker. This puts management reserve in the baseline. It sits outside the baseline and needs approval to use.
- D is weaker. This swaps the two reserves.
Question 5: Using reserves
Midway through a project, a supplier the team never considered a risk closes, and a replacement will cost $18,000 more. The event was not in the risk register. What should the project manager do first?
- A. Draw the $18,000 from contingency reserve, since that is what reserves are for
- B. Follow the change process to request management reserve, because the event was not an identified risk
- C. Absorb the cost in the estimate at completion and report it at closing
- D. Cut scope by $18,000 so the baseline stays intact
Best answer: B. Contingency reserve covers identified risks. An event nobody identified is what management reserve is for, and using it changes the cost baseline, so it goes through change control and the approval the governance plan sets.
- A is weaker. Contingency reserve is assigned to the risks in the register. Spending it on an unlisted event leaves the listed risks unfunded.
- C is weaker. Hiding a known overrun until closing breaks the reporting the outline asks for ("communicate the status of a risk impact").
- D is weaker. Cutting scope may be one option, but it is a decision for the change process, not a first step the project manager takes alone.
Practice questions: choosing a response
Question 6: Threat response
Part of the work needs specialist welding that your team has never done. The cost could run well over estimate. You award that work to an experienced firm under a firm-fixed-price contract. Which response strategy is this?
- A. Avoid
- B. Mitigate
- C. Accept
- D. Transfer
Best answer: D. The financial impact of an overrun moves to the vendor, who must deliver at the fixed price. Shifting impact and ownership to a third party is transfer.
- A is weaker. Avoid would remove the work or change the design so the welding is not needed.
- B is weaker. Mitigate would lower the chance or size of the overrun inside the project, for example by training the team.
- C is weaker. Accept would keep the work in house and set aside a reserve or do nothing.
Question 7: Outside your authority
The finance department plans a company-wide switch of accounting systems next quarter. It will delay invoice approvals for every project, including yours. What should you do with this risk?
- A. Escalate it to the program or portfolio level that owns the change, and confirm they accept ownership
- B. Mitigate it by hiring a contractor to process your invoices
- C. Accept it passively, since you cannot control finance
- D. Avoid it by moving all payments forward into this quarter
Best answer: A. The cause sits outside the project and affects other projects. Escalation hands the risk to the level that can act on it. It is complete when that owner accepts it; the project then stops managing it, though it may keep a note in the register.
- B is weaker. A contractor cannot speed up approvals inside a system the company controls, and it treats an organizational risk as yours alone.
- C is weaker. Passive acceptance ignores a risk someone else can manage. Escalation exists for exactly this case.
- D is weaker. Paying early may breach contract terms and does not remove the delay for later invoices.
Question 8: Opportunity response
The contract pays a bonus if the project finishes two weeks early. The team thinks an early finish is possible but not likely. You add a second shift for the final phase to raise the odds. Which strategy is this?
- A. Exploit
- B. Share
- C. Enhance
- D. Accept
Best answer: C. A second shift raises the probability of an early finish without guaranteeing it. Raising probability or impact is enhance.
- A is weaker. Exploit tries to make the opportunity certain, for example by changing scope so the bonus condition is met for sure.
- B is weaker. Share would bring in a partner better placed to capture the bonus and split it.
- D is weaker. Accept would take no action and simply welcome the bonus if it came.
Question 9: When a risk becomes an issue
The register lists "key tester leaves" with a trigger of a resignation notice, an owner, and a contingency plan to bring in a contract tester. The tester resigns today. What happens next?
- A. Re-run quantitative risk analysis on the whole register before acting
- B. Escalate to the sponsor and wait for direction
- C. Add a new risk to the register describing the resignation
- D. The risk owner carries out the planned contingency response, and the event is recorded in the issue log
Best answer: D. The trigger has fired, so the risk is now an issue. The response was planned for this moment and the owner is named, so the owner acts and the team tracks it as an issue. The outline lists "recognize when a risk becomes an issue" as a separate skill.
- A is weaker. A full re-analysis delays a response that was already agreed.
- B is weaker. Escalation is for risks outside the project's authority. This one has an owner and a plan inside the project.
- C is weaker. The event has happened. It is no longer uncertain, so it does not belong in the register as a new risk.
Question 10: Is the response worth it?
A threat has a 30% probability and a $60,000 impact. A mitigation costing $9,000 would cut the probability to 10% with the same impact. Is the mitigation worth funding on expected value alone?
- A. No: it costs $9,000 and saves only $6,000
- B. Yes: it lowers the EMV by $12,000, which is $3,000 more than it costs
- C. Yes: it saves the full $18,000 EMV
- D. No: a mitigation cannot be valued until the risk occurs
Best answer: B. EMV before = 0.30 x 60,000 = 18,000. EMV after = 0.10 x 60,000 = 6,000. Reduction = 12,000. Net of the $9,000 cost, the response is worth $3,000.
- A is weaker. $6,000 is the EMV left after mitigation, not the saving.
- C is weaker. The threat does not disappear. Expected loss falls from $18,000 to $6,000, not to zero.
- D is weaker. Comparing expected value before and after a response is how responses are justified in planning.
Question 11: Risk in an agile team
An agile team is unsure whether a third-party payment service will work with its platform. If it fails late, several sprints of work would be wasted. What is the best way to deal with this risk?
- A. Log it in the register and wait for the next phase gate review
- B. Ask the product owner to remove the payment feature
- C. Schedule a time-boxed spike early in the backlog to test the integration
- D. Add 20% to every story estimate to cover the uncertainty
Best answer: C. A spike is a short experiment that answers a technical question. Putting it early means the team learns cheaply before building on the assumption. This is how adaptive teams reduce risk through backlog order.
- A is weaker. Agile teams do not wait for phase gates, and a register entry does not reduce the risk.
- B is weaker. Removing a feature the customer needs is avoidance at a high cost to value, and should be a last resort.
- D is weaker. Padding every estimate hides the risk and does not answer the question.
Question 12: A new risk from a response
You transferred a cost risk by signing a fixed-price contract with a small vendor. A week later you learn the vendor is in financial trouble and may not finish. How should you treat this?
- A. As a secondary risk: add it to the register with an owner and a planned response
- B. As a residual risk: accept it, since the original risk is already handled
- C. As an issue: start a workaround immediately
- D. No action is needed, since the risk now belongs to the vendor
Best answer: A. A secondary risk is one created by carrying out a response. The fixed-price contract created exposure to the vendor failing, which needs its own owner and response, such as performance bonds or a backup supplier.
- B is weaker. Residual risk is what remains of the original risk after the response. Vendor failure is a new risk, not leftover cost risk.
- C is weaker. The vendor has not failed yet, so it is still a risk, not an issue.
- D is weaker. Transfer moves the cost impact, not the delivery risk. If the vendor fails, your project is still late.
How should you study risk for the PMP?
- Learn the response strategies as pairs of actions and signals. On the exam, the signal (insurance, second shift, other projects affected) usually decides the answer.
- Practice EMV and decision trees until you can do them in under a minute. Write probability x impact for each branch before you add anything.
- Keep the two reserves apart: contingency is inside the cost baseline for known risks, management reserve is outside it for unknown ones.
- Watch for the risk-to-issue moment. Once the trigger fires, the planned response and the issue log take over.
- For agile and hybrid items, look for answers that reduce uncertainty early, such as spikes, short iterations and frequent reviews.
Risk questions often blend with procurement, since contracts are a transfer tool. The PMP procurement and contract math practice set works through contract types and incentive fees. To see how these items fit the wider domain, read the Business Environment domain guide, and for a short mixed quiz the free PMP practice questions are open to everyone.
References
Help us improve this guide
How helpful was this article?
One tap helps us understand what’s useful.
Frequently asked questions
Mostly through Business Environment Task 5, "Plan and manage risk," plus reserves in Process Task 6 and the risk-to-issue handoff in Business Environment Task 4. Questions are usually scenarios that ask for the best response or the meaning of a calculation.
Expect to. EMV is probability times impact, with threats negative and opportunities positive. Decision trees apply the same idea to each branch and compare the expected totals.
Contingency reserve funds identified risks and is part of the cost baseline. Management reserve funds unidentified risks, sits in the budget outside the baseline, and needs approval through the change process to use.
When it is outside the project's authority or affects other projects or the organization. Escalation is complete when the owner at the higher level accepts it.
A new risk that arises from carrying out a risk response, such as vendor failure after transferring work to a fixed-price vendor. It needs its own owner and response.
Keep practicing for the PMP.
Review the study tools, access options and price, or start with free practice.
Related Articles
PMP Procurement Questions: Contract Types and Incentive Fee Math
Twelve original PMP procurement problems: choosing FFP, FPIF, CPFF, CPIF or T&M, incentive fee and ceiling math, point of total assumption, make or buy, and claims.
PMP Formulas in Practice: 12 Earned Value, PERT and Critical Path Problems
Work 12 original PMP calculation problems with every step shown: CPI, SPI, three EAC formulas, TCPI, PERT, float and velocity, mapped to the July 2026 outline.
Business Environment Is Now 26% of the PMP Exam: The Complete Domain Guide
Business Environment is 26% of the July 2026 PMP exam — roughly 44 of 170 scored questions, up from 8%. Every ECO task, what the enablers actually say, and eight practice scenarios.