Procurement questions mix judgment with arithmetic. Some ask which contract type fits a situation. Others give you a target cost, a share ratio and a ceiling and ask what the buyer pays. Both kinds are fast once you have a routine, and both lose points when the routine skips a step.
This set gives you that routine. For the full course with timed mocks across all three domains, see the PMP exam prep course. The contract type definitions are summarized in the procurement contract types notes, and the Process domain guide explains where procurement sits among the other Process tasks.
What does the 2026 PMP outline say about procurement?
Process is 41% of the exam. Its Task 5 lists ten enablers: plan procurement; execute a procurement management plan; select preferred contract types; evaluate vendor performance; verify objectives of the procurement agreement are met; participate in agreement negotiations; determine a negotiation strategy; manage suppliers and contracts; plan and manage the procurement strategy; develop a delivery solution. Task 6 on finance adds "monitor financial variations," which is where incentive math meets the budget.
Which contract types should you know?
The PMP uses the same contract names as US federal contracting. The Federal Acquisition Regulation, Part 16, gives the clearest public definitions, quoted in short below.
| Type | How the price works | Cost risk sits with | Fits when |
|---|---|---|---|
| Firm fixed price (FFP) | Price "not subject to any adjustment on the basis of the contractor's cost experience" | Seller (maximum) | Scope is well defined |
| Fixed price incentive fee (FPIF) | Target cost, target profit, a price ceiling and a profit adjustment formula | Shared, up to the ceiling | Scope is defined but cost has some uncertainty |
| Cost plus fixed fee (CPFF) | Allowable costs plus a fee "fixed at the inception of the contract" | Buyer | Scope is uncertain, such as research |
| Cost plus incentive fee (CPIF) | Costs plus a fee adjusted by formula, within a minimum and maximum fee | Mostly buyer, shared through the fee | Uncertain scope, but the buyer wants cost control |
| Time and materials (T&M) | Fixed hourly rates plus actual materials cost | Buyer | Extent or duration of work cannot be estimated at the start |
How do you calculate incentive contracts?
- Overrun or underrun = actual cost minus target cost.
- Seller's share = overrun or underrun x the seller's share ratio. In a 70/30 split, the buyer's share comes first, so the seller takes 30%.
- Final profit or fee = target profit or fee minus the seller's share of an overrun, or plus its share of an underrun.
- FPIF price = actual cost + final profit, but never above the ceiling price.
- CPIF fee stays between the minimum and maximum fee; the buyer pays actual cost + fee.
- Point of total assumption (PTA) = (ceiling price - target price) / buyer's share ratio + target cost. Above PTA, every extra dollar of cost comes out of the seller's profit.
These are original PrepSolution practice questions, not PMI exam items. Questions 4 to 6 share one FPIF contract: target cost $200,000, target profit $20,000 (target price $220,000), share ratio 70/30 buyer/seller, ceiling price $240,000.
Practice questions: choosing a contract
Question 1: Who carries the risk
Under which contract type does the seller carry the most cost risk?
- A. Cost plus fixed fee
- B. Firm fixed price
- C. Time and materials
- D. Cost plus incentive fee
Best answer: B. The FFP price does not change with the seller's actual costs, so every overrun reduces the seller's profit. FAR 16.202-1 describes it as placing "maximum risk and full responsibility for all costs" on the contractor.
- A is weaker. The buyer reimburses all allowable costs and the fee is fixed, so the buyer carries the cost risk.
- C is weaker. The buyer pays for every hour worked at the agreed rate, so longer work costs the buyer more.
- D is weaker. The seller's fee falls with overruns, but costs are still reimbursed, so most cost risk stays with the buyer.
Question 2: Urgent work with unclear scope
A data center outage needs outside engineers to start tomorrow. Nobody can yet say how many days the repair will take. Which contract type fits best?
- A. Firm fixed price
- B. Fixed price incentive fee
- C. Cost plus incentive fee
- D. Time and materials
Best answer: D. T&M pays agreed hourly rates plus materials. FAR 16.601 limits it to cases where it is "not possible ... to estimate accurately the extent or duration of the work," which matches an open-ended repair that must start now. A not-to-exceed amount and close monitoring protect the buyer.
- A is weaker. A seller cannot price a fixed amount for work nobody can size, and negotiating one would delay the start.
- B is weaker. FPIF needs a negotiated target cost, which nobody can set yet.
- C is weaker. CPIF also needs a target cost and fee formula, and is built for larger efforts than an emergency call-out.
Question 3: Research with uncertain scope
Your organization wants a vendor to develop a prototype using a material that has never been used in this product. The vendor will not commit to a fixed price. Which contract type is most appropriate?
- A. Cost plus fixed fee
- B. Firm fixed price
- C. Fixed price incentive fee
- D. Time and materials with no ceiling
Best answer: A. When the work is new and its cost cannot be predicted, the buyer reimburses costs and pays a fixed fee. FAR 16.306 notes this type "permits contracting for efforts that might otherwise present too great a risk to contractors."
- B is weaker. A fixed price would push all the uncertainty onto a vendor who has already refused it.
- C is weaker. FPIF still caps the price at a ceiling, which the vendor cannot price without knowing the cost.
- D is weaker. T&M with no ceiling gives the buyer no limit and the seller no incentive to control cost, which FAR 16.601 flags.
Practice questions: incentive math
Question 4: FPIF underrun
Using the shared FPIF contract, the seller finishes with an actual cost of $180,000. What are the seller's final profit and the price the buyer pays?
- A. Profit $20,000; price $200,000
- B. Profit $34,000; price $214,000
- C. Profit $26,000; price $206,000
- D. Profit $26,000; price $220,000
Best answer: C. Underrun = 200,000 - 180,000 = 20,000. Seller share = 20,000 x 0.30 = 6,000. Final profit = 20,000 + 6,000 = 26,000. Price = 180,000 + 26,000 = 206,000, which is under the $240,000 ceiling.
- A is weaker. This ignores the share ratio. Under an incentive contract the seller gains from an underrun.
- B is weaker. This gives the seller the buyer's 70% share of the underrun (14,000).
- D is weaker. The profit is right but the price is not. The buyer pays actual cost plus profit, not the target price.
Question 5: FPIF overrun and the ceiling
Using the shared FPIF contract, actual cost comes in at $230,000. What does the buyer pay, and what is the seller's profit?
- A. $241,000; profit $11,000
- B. $250,000; profit $20,000
- C. $240,000; profit $10,000
- D. $230,000; profit $0
Best answer: C. Overrun = 230,000 - 200,000 = 30,000. Seller share = 30,000 x 0.30 = 9,000. Formula profit = 20,000 - 9,000 = 11,000, so the formula price is 230,000 + 11,000 = 241,000. That is above the $240,000 ceiling, so the buyer pays $240,000 and the seller's profit is 240,000 - 230,000 = 10,000.
- A is weaker. This is the formula price before the ceiling is applied. The last step is always to check the ceiling.
- B is weaker. This keeps the full target profit, as if the seller bore none of the overrun.
- D is weaker. The seller still earns a profit, because $230,000 is below the ceiling.
Question 6: Point of total assumption
For the shared FPIF contract, at what actual cost does the seller start to absorb every additional dollar?
- A. $228,571
- B. $240,000
- C. $220,000
- D. $266,667
Best answer: A. PTA = (ceiling price - target price) / buyer share + target cost = (240,000 - 220,000) / 0.70 + 200,000 = 28,571.43 + 200,000 = 228,571.43. At that cost the formula price reaches exactly $240,000.
- B is weaker. $240,000 is the ceiling price, not a cost.
- C is weaker. $220,000 is the target price.
- D is weaker. $266,667 divides by the seller's share (0.30) instead of the buyer's (0.70): 20,000 / 0.30 + 200,000.
Question 7: Cost plus fixed fee
A CPFF contract has an estimated cost of $500,000 and a fixed fee of $40,000. Actual allowable costs are $560,000 and the scope did not change. What does the buyer pay?
- A. $540,000
- B. $604,800
- C. $560,000
- D. $600,000
Best answer: D. The buyer reimburses allowable cost and pays the fee, which "does not vary with actual cost" (FAR 16.306). 560,000 + 40,000 = 600,000.
- A is weaker. This pays the estimated cost plus the fee, but the buyer reimburses actual allowable costs.
- B is weaker. This treats the fee as 8% of cost (40,000 / 500,000) and applies it to the actual cost. The fee is a fixed amount.
- C is weaker. This leaves out the fee.
Question 8: CPIF underrun
A CPIF contract has a target cost of $300,000, a target fee of $24,000, a share ratio of 80/20 buyer/seller, a minimum fee of $10,000 and a maximum fee of $40,000. Actual cost is $260,000. What is the total the buyer pays?
- A. $284,000
- B. $292,000
- C. $332,000
- D. $300,000
Best answer: B. Underrun = 300,000 - 260,000 = 40,000. Seller share = 40,000 x 0.20 = 8,000. Fee = 24,000 + 8,000 = 32,000, inside the $10,000 to $40,000 range. Total = 260,000 + 32,000 = 292,000.
- A is weaker. This pays only the target fee and ignores the incentive.
- C is weaker. This adds the right fee to the target cost. The buyer reimburses actual cost, $260,000, not the target.
- D is weaker. This is the target cost, not what is paid.
Question 9: CPIF overrun and the minimum fee
Using the same CPIF terms, actual cost is $400,000. What does the buyer pay?
- A. $410,000
- B. $404,000
- C. $424,000
- D. $380,000
Best answer: A. Overrun = 400,000 - 300,000 = 100,000. Seller share = 100,000 x 0.20 = 20,000. Formula fee = 24,000 - 20,000 = 4,000, which is below the $10,000 minimum, so the fee is $10,000. Total = 400,000 + 10,000 = 410,000.
- B is weaker. This uses the formula fee of $4,000 and forgets the minimum fee.
- C is weaker. This pays the target fee as if there were no incentive.
- D is weaker. A cost-reimbursable contract pays allowable costs, so the total cannot fall below $400,000.
Question 10: Time and materials
A T&M agreement pays $95 an hour for a specialist. The specialist works 120 hours and uses $3,400 of parts. What is the invoice?
- A. $11,400
- B. $14,800
- C. $16,280
- D. $12,400
Best answer: B. Labor = 120 x 95 = 11,400. Materials at actual cost = 3,400. Invoice = 11,400 + 3,400 = 14,800.
- A is weaker. This is labor only.
- C is weaker. This adds 10% overhead on top. Under FAR 16.601 the hourly rate already includes overhead, general and administrative expense and profit.
- D is weaker. This adds $1,000 of materials instead of $3,400.
Practice questions: make or buy, and managing the contract
Question 11: Make or buy
Making a part needs $18,000 of tooling plus $40 a unit. Buying it costs $70 a unit. The project needs 500 units. What should the team do?
- A. Make, because the unit cost is $30 lower
- B. Make, because tooling can be reused on later projects
- C. Buy, because 500 units is above the break-even point
- D. Buy, because 500 units is below the 600-unit break-even point
Best answer: D. Break-even = 18,000 / (70 - 40) = 600 units. At 500 units, making costs 18,000 + 40 x 500 = 38,000 and buying costs 70 x 500 = 35,000, so buying saves $3,000.
- A is weaker. The unit saving only pays off after the tooling is recovered, at 600 units.
- B is weaker. Reuse could change the decision, but nothing in the question says later projects need the part.
- C is weaker. The conclusion is right but 500 is below break-even, not above it. Above 600 units, making would win.
Question 12: A disputed change
A vendor on a fixed-price contract says your engineer asked for extra features in a phone call and sends an invoice for the work. The contract requires changes in writing. What should the project manager do first?
- A. Pay the invoice to protect the relationship
- B. Refuse payment and refer the matter to the legal department
- C. Treat it as a claim: review it against the contract and change log and try to settle it by negotiation
- D. Ask the engineer to sign a backdated change order
Best answer: C. A contested change is a claim. The outline asks you to "manage suppliers and contracts" and "participate in agreement negotiations," and negotiation is the preferred first step for claims before any formal dispute process.
- A is weaker. Paying an unapproved change bypasses change control and sets a precedent.
- B is weaker. Going straight to lawyers skips negotiation, which is the usual first step and costs far less.
- D is weaker. Backdating a document misrepresents what happened and breaks PMI's Code of Ethics.
How should you study procurement for the PMP?
- Rank the five contract types by who carries cost risk, from FFP (seller) to CPFF and T&M (buyer). Many choice questions resolve from that ranking.
- For every incentive problem, write three lines: the variance, the seller's share, then the ceiling or fee limits. Most wrong answers skip the third line.
- Memorize PTA as a formula you can rebuild: the room between ceiling and target price, divided by the buyer's share, added to target cost.
- For contract management scenarios, the answer follows the contract: written change control, claims through negotiation, then the agreed dispute process.
Contracts are also a risk response, so practice the two together with the PMP risk management practice set. For earned value and schedule math, use the PMP formulas practice problems. The free PMP practice questions give a short timed mix across all domains.
References
- [1] Project Management Institute (2026). Project Management Professional (PMP) Examination Content Outline, July 2026. PMI. PMI
- [2] US General Services Administration and others (2026). Federal Acquisition Regulation, Subpart 16.2: Fixed-Price Contracts. Acquisition.gov. Acquisition.gov
- [3] US General Services Administration and others (2026). Federal Acquisition Regulation, Subpart 16.3: Cost-Reimbursement Contracts. Acquisition.gov. Acquisition.gov
- [4] US General Services Administration and others (2026). Federal Acquisition Regulation, Subpart 16.4: Incentive Contracts. Acquisition.gov. Acquisition.gov
- [5] US General Services Administration and others (2026). Federal Acquisition Regulation, Subpart 16.6: Time-and-Materials, Labor-Hour, and Letter Contracts. Acquisition.gov. Acquisition.gov
- [6] Project Management Institute (2025). A Guide to the Project Management Body of Knowledge (PMBOK Guide), Eighth Edition. PMI. PMI
Help us improve this guide
How helpful was this article?
One tap helps us understand what’s useful.
Frequently asked questions
Yes. Process Task 5, "Plan and manage procurement," covers planning procurement, selecting contract types, negotiating agreements, evaluating vendor performance and managing suppliers and contracts.
Firm fixed price. The price does not change with the seller's costs, so the seller absorbs any overrun.
PTA = (ceiling price - target price) / buyer's share ratio + target cost. Above that cost, the seller pays every additional dollar because the price has reached the ceiling.
When the extent or duration of the work cannot be estimated at the start, such as urgent repairs or staff augmentation. Buyers usually add a not-to-exceed amount and monitor hours closely.
Treat it as a claim, check it against the contract and change records, and try to settle it by negotiation before using the contract's formal dispute process.
Keep practicing for the PMP.
Review the study tools, access options and price, or start with free practice.
Related Articles
PMP Risk Management Practice Questions: Responses, EMV and Reserves
Work 12 original PMP risk questions: EMV, decision trees, contingency vs management reserve, threat and opportunity responses, and agile spikes, with every step shown.
PMP Formulas in Practice: 12 Earned Value, PERT and Critical Path Problems
Work 12 original PMP calculation problems with every step shown: CPI, SPI, three EAC formulas, TCPI, PERT, float and velocity, mapped to the July 2026 outline.
PMP Process Domain: The Largest Domain, Task by Task
Process is 41% of the July 2026 PMP exam. Here are its ten tasks, what each tests, and three worked questions, including an earned value calculation and a contract type choice.