the sponsor signs the charter, not the PM

Project Charter and Business Case

1

Document

The charter that authorizes the project

Sponsor

Signs It

The sponsor, not the PM, signs the charter

4

Financials

NPV, IRR, Payback, BCR in the business case

the document that makes the project real

Anatomy of a Charter

PROJECT CHARTER

v1.0 · FY26-Q2

Checkout Redesign Initiative

purpose · why this project exists

Reduce cart abandonment from 68% to 45% by simplifying the three-step checkout.

budget

$850,000

target launch

Aug 15, 2026

high-level objectives

  • › Reduce friction from 3 steps to 1
  • › Pass WCAG 2.1 AA accessibility
  • › Support 4 payment providers

assigned PM · authorized to spend

Amelia Chen

key risks · high-level

Payment provider API stability · Legal review for new T&Cs · Holiday freeze window

sponsor authorization

M. Rodriguez

Marco Rodriguez · VP Product

Apr 14, 2026

APPROVED

how to read this

  • › The charter is a one-page document (ish). Not a detailed plan — that comes later.
  • › It answers four questions: why (purpose), what (high-level objectives), who (PM + stakeholders), and how much (budget, deadline).
  • › The sponsor signs it, not the PM. That signature is the PM's permission to spend money and commit resources.
  • › Without a signed charter, the project officially does not exist. Any work before that point is at-risk.

Exam Traps

The PM does not write or sign the charter

The sponsor authorizes the project by signing the charter. The PM is named in the charter but does not author it.

Charter defines authority, not details

The charter gives the PM authority to spend resources. Detailed planning happens after the charter, in the project management plan.

Business case comes first

The business case justifies the project. The charter authorizes it. Business case is input, charter is output of initiating.

Assumptions and constraints belong in the charter

High-level assumptions, constraints, and risks are documented in the charter. The exam tests what is and is not in the charter.

Charter unlocks work

No charter, no project. The sponsor's signature is your permission to act.

Business case ≠ charter

Business case justifies. Charter authorizes. Two separate documents.

1
The Business Case

You write up why the kitchen needs remodeling — home value, family needs, broken appliances. Numbers attached. This goes to the decision-maker.

2
The Sponsor Decides

Your spouse reviews the case, agrees it is worth doing, and signs off. That is the charter — formal authorization.

3
You Are Named

The charter names you as the person running the remodel. It gives you authority to hire contractors and spend within the budget.

4
Detailed Planning Comes Next

The charter is a high-level permission slip. The detailed plan — schedule, vendors, color choices — comes after.

Case then charter. Sponsor signs, PM runs.
reading is not enough, you gotta practice

Ready to test your PMP knowledge?

1,800 practice questions written by certified professionals.

Start Practicing PMP
Reviewed by Chris K., PrepSolution Content Editor, Project Management
Sources verified against PMI 2026 standards
Updated May 2026