the longest path determines your project end date

Critical Path Method

0

Critical Path Float

Zero float activities define the project duration

2

Compression Options

Fast tracking first, crashing second

4

Dependency Types

FS, SS, FF, SF under precedence diagramming

red boxes are critical, delay any of them and the project slips

Network Diagram

ES 0 EF 3Ad 3 float 0ES 3 EF 7Bd 4 float 0ES 3 EF 5Cd 2 float 2ES 7 EF 12Dd 5 float 0ES 5 EF 8Ed 3 float 4ES 12 EF 14Fd 2 float 0critical path · A → B → D → F · 14 days

Compression · Try Order

1

Fast Track

Run sequential activities in parallel. No added cost. Watch for rework risk.

2

Crash

Add resources to critical-path activities. Adds cost. Only if resource-bound.

how to read this

  • › The diagram above shows a network of activities. Each box has ES (earliest start), EF (earliest finish), duration, and float.
  • Red boxes are on the critical path — the longest chain from start to finish. Zero float means any slip delays the whole project.
  • Blue boxes have float — they can slip (by their float amount) without affecting the end date.
  • › When you need to shorten the schedule, always try Fast Track first (free) before Crashing (costly).
  • › Compression only helps if you compress activities on the critical path. Compressing a floaty activity changes nothing.

Exam Traps

Fast tracking is tried before crashing

Fast tracking increases risk but not cost. Crashing increases cost. PMI expects you to exhaust the cheaper option first. When the question asks "what should the PM try FIRST," fast tracking is the answer unless risk is unacceptable.

Resource leveling can extend the critical path, smoothing cannot

Resource leveling resolves overallocation by delaying tasks, which can push out the end date. Resource smoothing only adjusts within available float. The exam tests this distinction directly.

Adding resources does not always shorten duration

Brooks' Law. Adding people to a late project can make it later because of training overhead and communication complexity. Crashing is only viable when the critical path activity is actually resource-constrained.

Near-critical paths become critical when activities slip

A path with 1 day of float is one delay away from being critical. Monitor near-critical paths, not just the one labeled "critical" today.

Zero float rule

Activities with zero float are on the critical path. A one-day delay there delays the whole project.

Fast track before crash

No cost increase first, cost increase second. That is the PMI preference order every time.

1
The Longest Dish Defines Dinner Time

You are hosting dinner. The roast takes 3 hours, the salad takes 15 minutes. Your critical path is the roast. Nothing you do to the salad changes when dinner starts.

2
Float Is Slack Time

You can prep the salad any time in the 3 hours while the roast cooks. That flexibility is float. The roast has zero float — start late, eat late.

3
Fast Tracking Means Parallel Cooking

Instead of waiting for the roast to rest before making gravy, start the gravy while the roast rests. You saved time at the risk of rushing. No extra cost, just more risk.

4
Crashing Means Extra Hands

Call a friend to chop vegetables in parallel. It costs you dinner for one more person, but it shortens the timeline. That is crashing.

Longest path wins. Zero float = critical. Fast track first, crash second.
reading is not enough, you gotta practice

Ready to test your PMP knowledge?

1,800 practice questions written by certified professionals.

Start Practicing PMP
Reviewed by Chris K., PrepSolution Content Editor, Project Management
Sources verified against PMI 2026 standards
Updated May 2026