burnup makes scope creep obvious, burndown hides it

Burndown, Burnup, and Cumulative Flow

3

Charts

Burndown, Burnup, Cumulative Flow Diagram

Burndown Direction

Tracks work remaining, falls over time

Burnup Direction

Tracks work completed, rises over time

three charts · each answers a different question

Three Agile Charts

Burndown

how much is left?

Line goes down. Ideal is dashed. Actual is solid.

Burnup

how much is done vs total?

Line goes up. Ceiling (scope) jumps when scope grows.

CFD

where is work stuck?

Bands per stage. Widening middle band = bottleneck.

how to read this

  • Burndown shows work remaining over time. Good when scope is locked — bad when scope changes silently (the line just looks slow).
  • Burnupshows work completed with a visible scope ceiling. Scope changes jump the ceiling, so they're obvious.
  • Cumulative Flow Diagramstacks bands for each workflow column. If the middle (In Progress) band fans open, WIP is piling up — that's a bottleneck, not productivity.

Exam Traps

Burnup shows scope changes, burndown does not

If scope grows mid-sprint, burnup charts show a rising ceiling. Burndown charts just look like you are falling behind.

Widening bands on a CFD mean trouble

A widening In Progress band on a cumulative flow diagram means WIP is accumulating and cycle time is rising.

Burndown is team-level, release burndown is project-level

Sprint burndown tracks one sprint. Release burndown tracks the whole release. The exam tests the scale.

Burnup for scope change

Burnup charts make scope creep visible. Burndown charts hide it.

Flat line is a warning

A burndown that is not falling means the team is not completing work. Investigate immediately.

1
Burndown

Count the pieces still in the box. Number should shrink every day until zero.

2
Burnup

Count the pieces placed in the puzzle. Number should grow toward total pieces. If a new bag of pieces appears, total goes up — scope change is obvious.

3
Cumulative Flow

A stacked area chart of pieces in each stage: unopened, sorted, placed, done. Widening bands mean pile-ups.

Burndown down, burnup up, CFD bands flat for health.
reading is not enough, you gotta practice

Ready to test your PMP knowledge?

1,800 practice questions written by certified professionals.

Start Practicing PMP
Reviewed by Chris K., PrepSolution Content Editor, Project Management
Sources verified against PMI 2026 standards
Updated May 2026