Network Diagrams and Dependencies

4

Dependency Types

FS, SS, FF, SF

2

Modifiers

Leads (overlap) and lags (delay)

2×2

Origin × Type

Mandatory/Discretionary × Internal/External

four types · but 95% of real life is FS

Four Dependency Types

Finish → Start · most commonPour foundationFrame wallsA must FINISH before B can START · real-life exampleStart → Start · parallel kickoffGrade siteTrench digB can't start until A has started · same crew moves togetherFinish → Finish · sync at the endWrite docsQA signoffBoth end together · you can't ship docs before testing is doneStart → Finish · rareDay shift startNight shift endNight can't leave until day arrives · shift handoffsLead vs Lag · FS with modifierslead · overlap (negative time)Start Build 2 days BEFORE Design finishes (FS − 2d)lag · delay (positive time)Concrete pour + 3 day cure before framing (FS + 3d)

how to read this

  • › Each pair shows an arrow from one activity to another. The label tells you which ends of the activities are connected.
  • FS(default) reads "the finish of A connects to the start of B." You see this everywhere.
  • Leads let the successor start before the predecessor finishes (overlap, saves time, adds risk).
  • Lags delay the successor (cure time, cool-down, mandatory wait).

Exam Traps

FS is the default, SF is rarest

Finish-to-Start is the most common dependency. Start-to-Finish is unusual and the exam tests whether you know when to use it.

Mandatory dependencies are hard logic

You cannot pour concrete before the foundation is dug. That is mandatory. Discretionary is preferred practice, not physics.

External dependencies are outside project control

A permit from city hall, a vendor delivery — these are external dependencies. Manage by engaging the external party early.

FS default

Finish-to-Start is the standard. Use others only when the work actually requires them.

Lead is not lag

A lead lets successor start earlier. A lag delays it. Easy to confuse.

1
Finish-to-Start

You must finish showering before you can get dressed. Classic FS.

2
Start-to-Start

You start the coffee and start feeding the cat at the same time. Both start together.

3
Finish-to-Finish

Writing the report and formatting the report finish together. Neither waits, but they end simultaneously.

4
Start-to-Finish

The night shift cannot end until the day shift starts. Rare but real.

FS default, SS parallel start, FF parallel end, SF takeover.
reading is not enough, you gotta practice

Ready to test your PMP knowledge?

1,800 practice questions written by certified professionals.

Start Practicing PMP
Reviewed by Chris K., PrepSolution Content Editor, Project Management
Sources verified against PMI 2026 standards
Updated May 2026