Integrated Change Control

CCB

Predictive Gate

All changes go through Change Control Board

PO

Agile Gate

Product Owner reprioritizes the backlog

0

Gold Plating Allowed

Adding unrequested features is always wrong

every change must pass through the CCB gate · no shortcuts

Integrated Change Control Flow

01Requestsubmit02Logchange log03Impactscope · sched · costCCBgateapprovedImplementupdate baselinerejectedClosedocumentedno bypass · not even for the sponsor

Scope Creep vs Gold Plating

scope creep · external

Customers or stakeholders push additions that slip in without change control. Originates outside the team.

gold plating · internal

The team adds unrequested features with good intentions. Originates from inside. Always wrong.

Exam Traps

The PM cannot approve scope changes unilaterally

Even when the sponsor asks directly, the change must go through the CCB. The PM documents and logs the request, the board decides. Bypassing the process is the classic trap.

Agile and predictive handle change differently

Predictive projects use a formal CCB. Agile projects welcome change through backlog reprioritization, owned by the Product Owner. The exam tests methodology-appropriate responses.

Gold plating is always wrong

Adding features the customer did not request is a defect, not a bonus. It introduces untested scope, increases cost, and violates the scope baseline.

Log the change, then analyze impact

The first action on a change request is to log it in the change log. Then analyze impact across scope, schedule, cost, and risk. Then send to CCB. The exam tests this sequence.

Never bypass the CCB

Not for the sponsor. Not for urgency. Not for friendly favors. The process protects the project.

Agile welcomes change

In agile, a change request becomes a backlog item the PO prioritizes. No CCB, no change log. That is the framework.

1
The Original Plan

You signed a contract to renovate the kitchen. Scope, budget, and schedule are all in writing. Everyone agreed.

2
Mid-Project Change Request

Halfway through, you decide you also want the dining room redone. That is a change request. You cannot just tell the contractor — it has to be documented and priced.

3
Impact Analysis

The contractor checks how the dining room affects the kitchen timeline, budget, and permits. Maybe it adds $15,000 and two weeks. Maybe it breaks a dependency.

4
Approval or Rejection

You and the contractor sign an amendment or you decide it is not worth it. Either way, the original contract stays intact until you formally agree.

Log it, analyze it, CCB it, implement it, update the plan.
reading is not enough, you gotta practice

Ready to test your PMP knowledge?

1,800 practice questions written by certified professionals.

Start Practicing PMP
Reviewed by Chris K., PrepSolution Content Editor, Project Management
Sources verified against PMI 2026 standards
Updated May 2026