Activities
Identification, Status Accounting, Verification, Audit
1
Source of Truth
Baselined artifacts, version-controlled
≠
Change Control
Configuration management is broader than change control
every baselined item has a history you can prove
Version Timeline
how to read this
- › Each dot is a baselined version of the product or document. Every change creates a new version.
- › The version number, the date, and the approved change request are all linked — that's status accounting.
- › The rejected branch shows that even failedchanges get recorded. "Never happened" is not acceptable bookkeeping.
- › Configuration audits check that the current real product matches the latest approved version. Drift is a finding.
Four Activities
Identification
Name and version every baselined item.
Status Accounting
Record what changed, who approved, when applied.
Verification
Confirm real state matches approved state.
Audit
Formal review. Findings become corrective actions.
Exam Traps
Configuration management and change control are related but different
Change control manages decisions about changes. Configuration management tracks what the product actually is across versions.
Every baselined item gets a version
Deliverables, documents, and designs all get version identifiers. Without versioning you cannot audit or reproduce results.
Audits verify conformance
Configuration audits check that the as-built state matches the approved configuration. Gaps are findings.
Baseline everything
If it changes and matters, version it. Scope, schedule, deliverables, documents.
Do not confuse the two
Change control decides. Configuration management records and audits.
Every version gets a name and number. v1.0, v1.1, v2.0. You know which one is current.
A change log tracks every edit. Who changed what, when, and why.
Periodic check that the document matches the approved version. Find and fix drift.