PrepSolution
PMPFrequently TestedProcess 41%
three EAC variants, three different conditions

EVM Interpretation and Forecasting

3

EAC Variants

Typical, atypical, and combined

TCPI

Recovery Index

What CPI the team must hit on remaining work

S

Curve Shape

Cost curve rises slowly, peaks, then flattens

same "today" · three possible finish-line forecasts

Three EAC Paths

PV · BACtoday#1#2#3ACEVtime →
#1

Typical · BAC / CPI

Current cost performance will continue. The default. Use when nothing suggests change.

#2

Atypical · AC + (BAC − EV)

The variance was a one-time event. Remaining work will hit original rate. Use when you know the cause and it's resolved.

#3

Combined · AC + (BAC − EV) / (CPI × SPI)

Both cost AND schedule problems will keep hurting you. Worst case forecast. Use when both indices are below 1.0.

how to read this

  • › The dashed line is PV — the original plan up to BAC.
  • › At "today" the green (EV) and amber (AC) tell you where you really are. EV is below AC, so you're over budget.
  • › Three different finish lines depending on which EAC formula matches the reality of your variance.
  • › Read the exam question carefully — it tells you which variant applies with phrases like "assume current performance continues" (→ #1) or "atypical variance" (→ #2).

Exam Traps

Match EAC variant to the question

Typical = BAC/CPI. Atypical = AC + (BAC − EV). Combined = AC + (BAC − EV)/(CPI × SPI). Read the condition carefully.

TCPI well above 1.0 is unrealistic

A TCPI of 1.25 means the team must be 25% more efficient on remaining work. At some point, replanning beats trying harder.

S-curves visualize planned vs actual spend

The S-curve shows PV, EV, and AC over time. Gaps between lines are variance. The exam tests chart interpretation.

Default EAC is BAC/CPI

Use it unless the question says "atypical" or "one-time." Then switch to AC + (BAC − EV).

High TCPI = replan

If TCPI demands miracles, stop trying harder and start replanning.

1
Typical

If the rest of the trip costs like the first leg, total cost = BAC/CPI. Use when cost performance is consistent.

2
Atypical

The cost overrun was a one-time thing. Remaining work will be back on budget. Use AC + (BAC − EV).

3
Combined

Schedule and cost are both off. Both matter. Use AC + (BAC − EV)/(CPI × SPI).

4
TCPI Reality Check

If TCPI says the team needs to triple efficiency, do not believe it. Replan.

Typical default, atypical reset, combined double-trouble, TCPI the reality check.
reading is not enough, you gotta practice

Ready to test your PMP knowledge?

1,800 practice questions written by certified professionals.

Start Practicing PMP
Reviewed by Chris K., PrepSolution Content Editor, Project Management
Sources verified against PMI 2026 standards
Updated May 2026