Schedule Compression
2
Techniques
Fast Tracking and Crashing
0
Fast Track Cost
No cost increase, only risk increase
+$
Crashing Cost
Always adds cost, sometimes shortens duration
same work, shorter timeline · two different levers
Before & After
how to read this
- › Top bar is the original plan. Design then build, sequential, 14 days.
- › Fast tracking starts the Build while Design is still wrapping up. Same people, same cost — but if Design changes, Build redoes work. Risk goes up.
- › Crashingkeeps the sequence but throws more people at each activity. Both shrink. You pay more. Brooks' Law warns this caps out fast.
- › PMI expects you to try fast tracking first. Crashing is the fallback when risk is unacceptable.
Exam Traps
Try fast tracking before crashing
Fast tracking is risk-only. Crashing is cost-only. PMI expects you to exhaust the free option first unless risk is unacceptable.
Only compress the critical path
Compressing a non-critical activity does not shorten the project. The exam tests whether you understand which path controls duration.
Crashing hits diminishing returns
Doubling the team does not halve the duration. Coordination overhead limits the benefit and Brooks' Law can reverse it.
Fast tracking increases rework risk
Running activities in parallel means downstream work might need to be redone if upstream assumptions change.
Fast track first
No cost, more risk. Always the first option PMI wants you to try.
Brooks' Law warning
Adding people to a late project can make it later. Crashing only helps if the activity is truly resource-bound.
You start editing while still writing the last paragraph. Risk: the conclusion might change and force re-edits. No cost.
You pay your friend to help format citations. It costs you but saves time — if your friend is useful.
Helping your friend with their math homework does not finish your essay. Compress only what is on YOUR critical path.
Adding three more friends just creates confusion and collisions. More resources do not always equal faster output.