fast track before crash, always in that order

Schedule Compression

2

Techniques

Fast Tracking and Crashing

0

Fast Track Cost

No cost increase, only risk increase

+$

Crashing Cost

Always adds cost, sometimes shortens duration

same work, shorter timeline · two different levers

Before & After

baseline · 14 daysDesign · 7dBuild · 7dday 14fast tracking · 10 days · no cost addedDesign · 7dBuild · 7dstarted early · 4d overlapday 10 · saved 4crashing · 10 days · +$$Design · 4dBuild · 6dadded 2 devs · each activity shortenedday 10 · saved 40d2d4d6d8d10d12d14d

how to read this

  • Top bar is the original plan. Design then build, sequential, 14 days.
  • Fast tracking starts the Build while Design is still wrapping up. Same people, same cost — but if Design changes, Build redoes work. Risk goes up.
  • Crashingkeeps the sequence but throws more people at each activity. Both shrink. You pay more. Brooks' Law warns this caps out fast.
  • › PMI expects you to try fast tracking first. Crashing is the fallback when risk is unacceptable.

Exam Traps

Try fast tracking before crashing

Fast tracking is risk-only. Crashing is cost-only. PMI expects you to exhaust the free option first unless risk is unacceptable.

Only compress the critical path

Compressing a non-critical activity does not shorten the project. The exam tests whether you understand which path controls duration.

Crashing hits diminishing returns

Doubling the team does not halve the duration. Coordination overhead limits the benefit and Brooks' Law can reverse it.

Fast tracking increases rework risk

Running activities in parallel means downstream work might need to be redone if upstream assumptions change.

Fast track first

No cost, more risk. Always the first option PMI wants you to try.

Brooks' Law warning

Adding people to a late project can make it later. Crashing only helps if the activity is truly resource-bound.

1
Fast Tracking the Essay

You start editing while still writing the last paragraph. Risk: the conclusion might change and force re-edits. No cost.

2
Crashing the Essay

You pay your friend to help format citations. It costs you but saves time — if your friend is useful.

3
Pick the Critical Path Only

Helping your friend with their math homework does not finish your essay. Compress only what is on YOUR critical path.

4
Diminishing Returns

Adding three more friends just creates confusion and collisions. More resources do not always equal faster output.

Fast track first, crash second. Only the critical path matters.
reading is not enough, you gotta practice

Ready to test your PMP knowledge?

1,800 practice questions written by certified professionals.

Start Practicing PMP
Reviewed by Chris K., PrepSolution Content Editor, Project Management
Sources verified against PMI 2026 standards
Updated May 2026